GC Contract and Change Order Reviewer

Review the GC contract and each change order the way an owner's rep and lender should

0 downloads on LenderSkills

Free · v1.0.0

Install it in one line — paste a single command into Claude, ChatGPT or Cursor and it writes the skill into your project.

Free, and about thirty seconds: a work email and a six-digit code.

Screened

Downloading shares your name, firm, role, and email with Avi Hacker, J.D.. That introduction is what keeps every skill here free.

What this skill does

Reads a general contractor or construction manager agreement and its exhibits the way an experienced owner's rep would, then tests each change order for entitlement, price and time. For developers negotiating the contract and for construction lenders that make contract review a condition of closing.

What it does

  • Maps which standard AIA sections were modified and quotes what the signed version actually says
  • Finds scope excluded on the GMP assumptions page, loose allowances, and contingency that never comes back to the owner
  • Tests delay damages, retainage against state law, lien waivers and closeout holdbacks
  • Checks bonds, builder's risk insurance, and whether the contract can be assigned to the construction lender
  • Reviews each change order in three passes — entitlement, pricing, time — and ranks every issue by dollar exposure

When to use it

  • A GC or CM agreement arrives for signature
  • A GMP amendment is delivered at the end of preconstruction
  • The construction lender requires contract review before closing
  • A change order or construction change directive needs a decision

What to have ready

  • The agreement, the general conditions as modified, and every exhibit
  • The schedule of values, allowances, and the insurance and bond exhibit
  • For change orders: the request, pricing backup and notice letters
  • The loan term sheet or agreement and the development budget

How to use it

  1. Download it with the button above. You'll sign in with a work email — that's how the creator knows who is using their skill.
  2. Copy the install prompt from the "Run it in Claude" box, and paste it into Claude along with the file. Claude installs the skill, fills in your firm's details where the file has [BRACKETED] placeholders, and runs a quick test with you.
  3. Then just ask in plain English. Claude picks the skill up on its own when a request matches it. Anything it still needs, it asks you for — it won't invent a number.

"Review this AIA A102 with GMP amendment for [PROJECT] and the three pending change orders. What has to change before the construction lender will close?"

What you get back

A contract rating and signing recommendation, tables for price, time, payment and risk transfer, a change order review table, and a ranked issues list with requested revisions and counsel referrals.

Good to know

  • Output quality tracks input quality. A missing figure is flagged as missing — it is never estimated to fill a gap.
  • Every draft is a starting point for your own review, not a finished decision.
  • Runs anywhere Claude does: the Claude app, Claude Desktop, or Claude Code.
  • This is a contract review from the owner's side, not the lender's decision on whether to fund a change. Contract interpretation, lien waiver sufficiency, liquidated damages enforceability and insurance adequacy are for counsel and a licensed broker in the project state.

Source & credit

Imported from Avi Hacker's open-source cre-agent-skills library (Apache-2.0). Author: Avi Hacker, J.D. (The AI Consulting Network) — https://github.com/ahacker-1/cre-agent-skills. LenderSkills added front matter so Claude can recognize the skill and removed a federal bond threshold and an AIA section number that could not be confirmed; it also appended a legal disclaimer, and the package header lists every change. The author's content is otherwise unmodified. Full credit to the author. Avi Hacker did not submit this listing and does not endorse it — the original is free at the link above.

Legal disclaimer

This skill drafts; it does not decide. Its output is not legal, tax, accounting, appraisal, or investment advice, and using it creates no attorney-client, fiduciary, or advisory relationship. Nothing it produces is a commitment to lend or an offer to sell a security. Verify every number, date, citation, and conclusion against the source documents, and have a qualified professional licensed in the relevant jurisdiction review the work before you rely on it or send it to a borrower, investor, counterparty, or regulator. Laws, rates, and market data change. The final work product is yours.

Inside this skill

The actual file you get. Members can read it in full before saving it.

Skill name
gc-contract-and-change-order-reviewer
What it does
Reviews a general contractor or construction manager agreement (stipulated sum, GMP, cost-plus) and its exhibits for price, time, payment, retainage, lien waivers, bonding, liquidated damages, indemnity and risk transfer, and gives each change order or construction change directive a disposition on entitlement, pricing and schedule impact, producing an issues list with negotiation positions.
When it runs
Trigger when a construction lender conditions closing on contract review, a GMP amendment arrives, a change order needs approval before it is funded, or a troubled project needs to know what the contract actually says.
License
Apache-2.0
Metadata
author: "Avi Hacker, J.D." organization: "The AI Consulting Network" homepage: https://www.theaiconsultingnetwork.com source: https://github.com/ahacker-1/cre-agent-skills copyright: "Copyright 2026 Avi Hacker, J.D. / The AI Consulting Network" upstream_commit: a9a4e29
Imported to LenderSkills.ai from the open-source cre-agent-skills library.
Author: Avi Hacker, J.D. - https://github.com/ahacker-1/cre-agent-skills
License: Apache-2.0. Copyright 2026 Avi Hacker, J.D. / The AI Consulting Network.
Licensed under the Apache License, Version 2.0 (see the repository LICENSE); redistributed with attribution.
Upstream file: skills/development/gc-contract-and-change-order-reviewer.md (commit a9a4e29)
Imported: 2026-09-28
Changes made by LenderSkills: added a name and description to the front matter so Claude can recognize the skill; removed specific federal bond dollar thresholds (subject to inflation adjustment and irrelevant to private work) and an A201 section number we could not confirm; noted in this header how linked skill names map to the LenderSkills catalogue. A legal disclaimer will be appended by LenderSkills at the end of the file. Otherwise the author's content is unmodified.
The knowledge/, research/ and skills/ files linked below live in the upstream repository. Most linked skills are also in the LenderSkills catalogue under the same name; the exceptions are Construction Draw and Cost-to-Complete Reviewer and Development IC Memo Writer (upstream only; the catalogue's construction-draw-reviewer covers draw review), and Quote Comparator and Term Sheet Builder (listed in the catalogue as lender-quote-comparator and loan-term-sheet-builder).

GC Contract and Change Order Reviewer

Review a general contractor or construction manager agreement and its exhibits for price, time, payment, and risk transfer, review individual change orders for entitlement, pricing, and schedule impact, and produce an issues list with negotiation positions.


When to Use This Skill

Reading the full skill counts as a download. The contributor receives your name, company, and email.

Ratings & reviews

★★★★★Rate this skill

No written reviews yet. If you run this on a live file, say how it went. The next lender reading this page is deciding whether to trust it.

Examination record

Archive inspectionPackage unpacked in isolation; contents and paths verified
Executable & binary blockExecutables, binaries, and scripts rejected automatically
Static analysisScanned for exfiltration, credential access, obfuscation, prompt injection
Human reviewA moderator read the skill end to end. Retired on 14 September 2026 — screening decides now.
What each gate checks

Run it in Claude

  1. Copy the install command above
  2. Paste it into Claude, ChatGPT or Cursor
  3. It writes the skill in, fills in your firm’s details, and test-runs it with you

Prefer the file? The prompt above is for a package you already downloaded.

New to skills? Read the 5-minute guide →

Details

Version1.0.0
AddedSep 29, 2026
UpdatedSep 29, 2026
CategoryDue Diligence
Downloads0
Tagsconstruction, GC contract, AIA, GMP, change order, retainage, lien waiver, due diligence