What this skill does

When a contractor or borrower submits a change order mid-build, this works out whether the change is real, who should pay for it, and whether the loan is still whole afterwards — then drafts the decision memo before the work goes ahead.

What it does

  • Sorts the change into a category — unforeseen condition, code requirement, design error, owner upgrade or contractor overrun — and says who normally bears the cost
  • Measures the cost and schedule impact, including what extra months do to the interest reserve and maturity
  • Decides the funding source: remaining contingency, genuine savings on other lines, or new borrower cash
  • Re-tests loan-to-cost, loan-to-value on completion and whether the as-complete value still holds
  • Flags whether the loan documents appear to require lender consent, and drafts an approve, approve-with-conditions or decline memo

When to use it

  • A change order or revised bid arrives mid-project
  • A borrower wants to use contingency
  • The schedule is slipping because of a scope change
  • Before the next draw, when a change is still unapproved

What to have ready

  • The change order and its supporting documents
  • The current budget with contingency used and remaining
  • The construction contract type
  • The change-order section of the loan documents, and the loan terms

How to use it

  1. Download it with the button above. You'll sign in with a work email — that's how the creator knows who is using their skill.
  2. Copy the install prompt from the "Run it in Claude" box, and paste it into Claude along with the file. Claude installs the skill, fills in your firm's details where the file has [BRACKETED] placeholders, and runs a quick test with you.
  3. Then just ask in plain English. Claude picks the skill up on its own when a request matches it. Anything it still needs, it asks you for — it won't invent a number.

"Change order #[N] on [ADDRESS]: the GC wants [AMOUNT] and [DAYS] more days for [REASON]. Contingency left is [AMOUNT]. Should we approve it, and who pays?"

What you get back

A decision memo with the change's category, cost and time impact, a before-and-after leverage table, the cash deposit the borrower must make to keep the loan in balance, a consent check, and numbered approval conditions.

Good to know

  • Output quality tracks input quality. A missing figure is flagged as missing — it is never estimated to fill a gap.
  • Every draft is a starting point for your own review, not a finished decision.
  • Runs anywhere Claude does: the Claude app, Claude Desktop, or Claude Code.
  • It never treats a change order as new loan money, and it flags contract and loan-document questions for counsel rather than deciding them.

Legal disclaimer

This skill drafts; it does not decide. Its output is not legal, tax, accounting, appraisal, or investment advice, and using it creates no attorney-client, fiduciary, or advisory relationship. Nothing it produces is a commitment to lend or an offer to sell a security. Verify every number, date, citation, and conclusion against the source documents, and have a qualified professional licensed in the relevant jurisdiction review the work before you rely on it or send it to a borrower, investor, counterparty, or regulator. Laws, rates, and market data change. The final work product is yours.

Inside this skill

The actual file you get. Members can read it in full before saving it.

Skill name
change-order-evaluator
What it does
Use when a borrower or contractor submits a change order on a construction or rehab loan and the lender has to decide whether to approve it and who pays for it. Trigger on "change order came in," "the GC wants more money," "evaluate this change order," "can they use contingency for this," "does this need lender approval," "unforeseen conditions," "the budget is going up $40k," "will this put the loan out of balance," "does this change LTC or the as-complete value," "the schedule is slipping a month because of this change," or when a change order form, revised bid, or engineer's letter is dropped in mid-project. Classifies the change, measures cost and time impact, decides the funding source (contingency, savings, or new borrower equity), re-tests LTC, value, and interest reserve, checks the loan documents' consent rules, and drafts a decision memo. Draft only; the lender approves.
What you give it
[change order and reason] [current budget, contingency remaining, loan terms]

Change Order Evaluator

A change order is where a construction loan quietly changes shape. The cost goes up, the schedule goes out, the contingency disappears on month three, and the draw reviewer only finds out when the loan is out of balance. The lender's questions are simple — is this change real, who pays for it, and is the loan still whole afterwards — but they have to be answered before the work is done, not after. This skill answers them and writes the memo.

Works for: ground-up and rehab loans with a holdback and a contingency, at any stage of the build. It evaluates one change (or a bundle submitted together). Line-by-line draw review stays with construction-draw-reviewer; the month-by-month reserve math stays with interest-reserve-calculator.


Step 1 — Intake

InputRequired?Notes
The change order✅Description, dollar amount, days added, who initiated it, signatures
Reason and support✅Engineer's or inspector's letter, code official's notice, revised bid, photos
Current schedule of values✅Budget by line, funded to date, remaining
Contingency✅Original, used to date, remaining — and every prior change order
Construction contract type✅Fixed price, cost-plus, or cost-plus with a guaranteed maximum — decides who bears overruns
Loan documents' change-order provisions✅Consent thresholds, what counts as a material change, balancing requirements
Loan terms✅Commitment, rate, maturity, interest reserve remaining, as-complete value
Latest inspection and cost-to-completeHelpfulTo test whether other lines are also running over
Plans and permit statusHelpfulWhether the change requires revised plans or a permit revision

Minimum viable: the change order, the schedule of values with contingency remaining, and the contract type. Without the loan documents' consent provisions, the memo says "consent requirement unconfirmed — read section [__] of the loan agreement" rather than guessing.


Step 2 — Classify the change

The category decides who should pay.

CategoryExampleUsual funding answer
Unforeseen site conditionRock, poor soils, buried debris, hidden rot in a rehabContingency first; contract may shift it to the owner

Reading the full skill counts as a download. The contributor receives your name, company, and email.

Ratings & reviews

★★★★★Rate this skill

No written reviews yet. If you run this on a live file, say how it went. The next lender reading this page is deciding whether to trust it.

Examination record

Archive inspectionPackage unpacked in isolation; contents and paths verified
Executable & binary blockExecutables, binaries, and scripts rejected automatically
Static analysisScanned for exfiltration, credential access, obfuscation, prompt injection
Human reviewA moderator read the skill end to end. Retired on 14 September 2026 — screening decides now.
What each gate checks

Run it in Claude

  1. Copy the install command above
  2. Paste it into Claude, ChatGPT or Cursor
  3. It writes the skill in, fills in your firm’s details, and test-runs it with you

Prefer the file? The prompt above is for a package you already downloaded.

New to skills? Read the 5-minute guide →

Details

Version1.0.0
AddedSep 29, 2026
UpdatedSep 29, 2026
CategoryDraw Management
Tagschange order, construction, contingency, loan in balance, draw management